Thursday, October 16, 2008

Objects on the calendar...

May be further away than the appear.

No changes since the last photos, but some schedule updates: Due to some QA issues with one of the cabinets, we are a little behind. One of the cabinets is warped, so it has to go (it's under warranty, and this is expensive- so FIX IT!). Unfortunately this puts us behind a bit while they get it built. We are now about a week behind- the exact order of things seems to be a little foggy- I'm having trouble getting the GC to commit, but then again I do that too- sometimes it doesn't matter what order certain things happen in, so you just go with the flow.

The likely next steps are: cabinet fixes and hardware on the 21st, countertop the 22nd, plumbing the 23rd/24th, backsplash the 29th, electrical the 29th/30th, trim and flooring either during the lull or after the electrical- TBD on that.

Like I said- a little fuzzy, but we're getting closer.